Is your equipment (boiler applications) ready for start-up? The following items
can be used to determine if you are.
| |
Is boiler/fired vessel and auxiliary equipment installation
completed in accordance with boiler/fired vessel company requirements?
-
Boiler feed pumps.
-
Water level permissive wiring terminated.
-
Has fuel pressure regulator system been installed to maintain constant supply
pressure and temperature.
-
Has vessel been hydrostatically tested?
|
| |
Are fuel and atomizing steam lines clean and free of any
debris?
-
Does purging of gas lines require certification, if so, has certification been
obtained?
-
Are strainers provided to prevent entry of foreign materials into fuel control
valves and safety devices?
-
Is lagging installed on hot lines fuel oil atomizing steam?
-
Is atomizing steam line trapped to atmosphere assuring dry atomizing steam?
|
| |
Will Coen be required to assist in boilout?
-
If so, has boiler company been contacted regarding boilout procedure?
|
| |
Are all fans/dampers required for combustion operable?
-
If fans are by other, has balancing been completed?
-
Have all damper position switch permissives been installed and wires
terminated?
|
| |
Has the flame safeguard system been wired and piped?
-
If applicable, is a programmable logic controller field terminal available on
site?
-
Should Coen provide a field terminal?
|
| |
Are flow measuring devices provided and operable to determine
capacity of either burner or fired vessel?
-
Steam flow
-
Feedwater flow
-
Gas fuel flow
-
Fuel oil flow
|
| |
Have provisions been
made for full load testing or ventilation?
|
| |
Is there ample fuel
supply to operate burner and pilot for start-up?
|
| |
Are there any items supplied on the project that are obviously
damaged, missing, or defective?
-
If so has the proper vendor been notified?
|
| |
Are taps and/or indicators provided
for the following indications:
|