Coen Company

Pre Start-Up Installation Form

* Required Fields
*Date: *Service Representative:
*Jobsite: *Location:
*Job Number:    

1. Is boiler/fired vessel and auxiliary equipment installation completed in accordance with boiler/fired vessel company requirements?
A. Boiler feed pumps. Yes No  N/A
B. Water level permissive wiring terminated. Yes No  N/A
C. Has fuel pressure regulator system been installed to maintain constant supply pressure and temperature. Yes No  N/A
D. Has vessel been hydrostatically tested? Yes No  N/A
2. Are fuel and atomizing steam lines clean and free of any debris? Yes No  N/A
A. Does purging of gas lines require certification, if so, has certification been obtained? Yes No  N/A
B. Are strainers provided to prevent entry of foreign materials into fuel control valves and safety devices? Yes No  N/A
C. Is lagging installed on hot lines; fuel oil? Yes No  N/A
D. Is lagging installed on hot lines; atomizing steam? Yes No  N/A
E. Is atomizing steam line trapped to atmosphere assuring dry atomizing steam? Yes No  N/A
3. Will Coen be required to assist in boilout? Yes No  N/A
A. If so, has the boiler company been contacted regarding boilout procedure? Yes No  
4. Are all fans/dampers required for combustion operable? Yes No  N/A
A. If fans are by another manufacturer, has balancing been completed? Yes No  N/A
B. Have all damper position switch permissives been installed and wires terminated? Yes No  N/A
5. Has the flame safeguard system been wired and piped? Yes No  N/A
A. If applicable, is a programmable logic controller field terminal available on site? Yes No  N/A
B. Should Coen provide a field terminal? Yes No  N/A
6. Are flow measuring devices provided and operable to determine capacity of either burner or fired vessel:
A. Steam flow? Yes No  N/A
B. Feedwater flow? Yes No  N/A
C. Gas fuel flow? Yes No  N/A
D. Fuel oil flow? Yes No  N/A
7. Have provisions been made for full load testing or ventilation? Yes No  N/A
8. Is there an ample fuel supply to operate burner and pilot for start-up? Yes No  N/A
9. Are there any items supplied on the project that are obviously damaged, missing, or defective? Yes No  N/A
A. If so has the proper vendor been notified? Yes No  
10. Are taps and/or indicators provided for the following indications:
A. Fuel gas supply pressure ? Yes No  N/A
B. Fuel gas at burner pressure? Yes No  N/A
C. Fuel oil supply pressure? Yes No  N/A
D. Fuel oil at burner pressure? Yes No  N/A
E. Fuel oil temperature? Yes No  N/A
F. Atomizing steam supply pressure? Yes No  N/A
G. Atomizing steam at burner pressure? Yes No  N/A
H. Windbox pressure? Yes No  N/A
I. Furnace pressure? Yes No  N/A
J. Stack daft pressure? Yes No  N/A
K. Stack temperature? Yes No  N/A
11. Are qualified operators available for start-up? Yes No  
12. State estimated date when above items will all be completed, allowing sufficient time for unexpected delays.
13. State desired starting date based on item 12 above. Please notify Coen Company, Foster City, CA, not less than 3 weeks in advance of this date to permit scheduling of service personnel and avoid delays.  
Your boiler/fired vessel instruction Manual and Coen Instructions and Drawings contain information concerning certain basic requirements for a new installation, and are intended to guide you in your plant for completing the installation and making it ready for initial operation.  If additional advice is required, consult with Coen. 

 

If all of the above work is not completed prior to arrival of our serviceman, the additional waiting or travel time and expenses caused by delay will be charged for all current per diem rate plus travel and living expenses.

 

List below the name, address and telephone number of the person located at the installation who is responsible for completion of the above work, so that we can communicate with him or her if necessary.